Proposal of Highway Products, Inc. to the City of Lansing
regarding changes in the TC-25 Coach
1 . Thirty thousand five hundred eighty nine dollars withheld
by the City of Lansing.
The City of Lansing is withholding $30 , 589 . 00 of the amount
designated for payment for the nine buses . It is the position
of Highway Products, Inc. that this money is now due and
payable and we request that the City Council authorize the
release and payment of the money prior to or at the same
time as execution of an agreement between Highway Products , Inc.
and the City of Lansing for additional work on the buses .
2 . Specific Changes proposed to meet the summary of defects as
proposed by Clare D. Loudenslager for the UMTA meeting on
January 15 , 1974 .
a) Transmissions .
Highway Products , Inc . recommends that the A-727 Chrysler
transmission be replaced with Detroit Diesel Allison
AT540 transmission. This transmission change will include:
1) new engine mounts , 2) heat shields , 3 ) new shift quadrant,
4) drive line, 5) oil cooler, 6) starters , and 7 ) accelerator
cables. (This item covers Items #1 , 3 , 5, 10 and 13 of
Loudenslager' s memo of 1-15-74) . This conversion is
estimated to cost approximately $2 , 000 per bus and it is
proposed that Highway Products , Inc. pay one half or
$1, 000 and the City of Lansing pay one half each unit.
This price includes the trade in of the Chrysler A-727
transmission.
b) Fuel System.
The City of Lansing asked that an estimate be prepared for
the conversion of the fuel system on nine buses from propane
to gasoline. It is proposed to replace the fuel tank with a
seventy gallon tank, new fuel lines, fuel filters, fuel door
on the curb side of the buses and engine conversion involving
manifold and electrical changes per Chrysler ' s recommendation.
The total cost of this conversion will be $1 , 203 . 27 per unit,
with the City of Lansing to pay total cost . (Item #4 in
Loudenslager ' s memo of 1-15-74) . All items removed from the
buses in order to make the fuel system conversion will be
donated to the City of Lansing.
Page 2
c) Suspension.
It is proposed that the suspension system of the bus be
changed in order to provide a softer ride and minimize
breakage to shock absorber mounts . This change will
involve raising the bus approximately one inch to provide
greater travel in both jounce and rebound modes . By raising
the bus approximately one inch the floor step height should
fall within the range of approximately fourteen inches .
This change involves replacement of shock absorbers with new
softer shocks, new "U" bolts , shackles and upper and lower
shock mounts front and rear as required. Highway Products,
Inc. will assume the total cost of this conversion.
(Item #2 in Loudenslager' s memo of 1-15-74) .
d) Air Cleaner Pans.
It is proposed that the air cleaner pans be replaced with a
new design with an elliptical hole which will facilitate
the removal of the air cleaner from the bus for servicing.
The cost of this item will be borne by Highway Products , Inc .
entirely. (Item #12 in Loudenslager ' s memo of 1-15-74) .
e) Fan Idler.
It is proposed to replace the spring loaded fan idler on
each bus with an idler of a new design. The cost will
be borne by Highway Products, Inc . in its entirety.
(Item #8 in Loudenslager ' s memo of 1-15-74) .
f) Steering Column "U" Joints .
Two damaged steering column "U" joints have been replaced
and Capitol Transit has been provided with three additional
spare joints which they have in stock. It is proposed that
Highway Products , Inc. examine each coach and replace as
required. (Item #7 in Loudenslager 's memo of 1-15-74) .
g) Steering Column Turn Signals .
Highway Products , Inc . has recommended to the City of Lansing
that a change be made in the type of turn signals used on the
buses . It is proposed to remove the steering column mounted
turn signal device and install on each bus a foot control
turn signal. This is a product improvement , however the
total cost of this change will be borne by Highway Products ,
Inc . (Item #7 in Loudenslager' s memo of 1-15-74) .
Page 3
h) Miscellaneous Electric Problems .
The City of Lansing has reported to Highway Products that
on a number of units there are some poor ground connections ,
shorts and so forth in the electric systems . Highway
Products will examine each bus , check all connectors possible,
retighten or relug and reband as required. Highway Products
is to assume total cost of this item. (Item #14 in
Loudenslager' s memo of 1-15-74) .
i) Bus Skins .
On some of the buses there is an indication of skin flexing
on the lower front corner of the curb side pier window.
This condition is not a result of any structural fault , but
is a matter of skin movement with buses engaged in normal
operations. It is proposed that some change be made in this
area, i. e. , additional rivets, stop hole or some such remedy
yet to be specifically determined . The cost of this work will
be borne by Highway Products .
3 . Where Work is to be Done.
At this particular time it is planned that the transmission work
be done by an authorized Chrysler representative somewhere
between Lansing and Detroit. The work involving the installation
of the new fuel tank and suspension system would be done at a
welding shop to be selected by Highway Products , Inc. The shop
should also be in the area between Lansing and Detroit . There
is a possibility that Highway Products, Inc . would request the
City of Lansing to permit the other work involved to be done in
its bus garage in Lansing.
4 . Estimated Time for Completion of Project .
It is hoped that this entire project could be completed within a
period of 90 days from date of final approval. It must be
understood that in this day of acute material shortages there
may be some difficulty in obtaining some of the materials . It
is not anticipated but there is that possibility. Effort will
be made by Highway Products , Inc. to perform this work as
expeditiously as possible in order to get the buses back on the
road. Since this work involves a considerable amount of time
on the part of Highway Products, Inc. field service group, it is
also to our advantage to perform this work in the minimum of time.
5 . Warranty.
a) The Allison AT-540 transmission will have a 75 , 000 mile
or 24 month warranty.
Page 4
b) The normal warranty on the bus will be extended for a
period of 90 days starting the day the nine buses are
redelivered and certified by the authorized representative
of the Michigan Public Service Commission that the scope
of the work as outlined in this proposal has been completed
on a satisfactory basis .
6 . Payment.
a) Before any work under this program would be started a balance
of $30 , 589 . 00 on the original contract will be paid.
b) If the proposal is accepted as outlined above and certified
by an authorized representative of the Michigan Public
Service Commission that the scope of the work as outlined
in this proposal has been completed on a satisfactory basis ,
payment will be made in net 20 days .
Richard W. Geaney
Vice President - Marketing
Highway Products , Inc.
789 Stow Street
Kent , Ohio 44240
February 19 , 1974
Resubmitted March 7 , 1974