Loading...
HomeMy WebLinkAbout1993 TIFA minutes03-18-94A10:10 RCVD TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING BOARD OF DIRECTOR'S MEETING 9TH FLOOR CONFERENCE ROOM, LANSING CITY HALL WEDNESDAY, JANUARY b, 1993 4:15 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Pandy, Jr,-, Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook; Barbara Foreman GUESTS PRESENT: Tom Galyon; Cora Huguely; Ken Lawless Chairman Lucile Belen brought the meeting to order at 4:11 p.m. 1) 2) APPROVAL OF THE DECEMBER 2, 1992 BOARD OF DIRECTOR'S MEETING MINUTES Motion - George Mills motioned the Board to approve the December 2, 1992 Board -)f Director's Meeting Minutes as printed and place them on file. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. SECRETARY'S REPORT A) Lansing Center Update TIFA Committee Chairman George Mills informed the Board than the Committee had met and discussed the recommendations from Clark Construction on the lowest qualified bidder for Bid Package #1 (Excavation & Concrete) and Bid Package # 3 (Structural Steel). It was the Committee's recommendation to the TIFA Board to support Clark's recommendation of awarding a contract to Granger Construction for Bid Package #1 and Douglas Steel Fabricating for Bid Package #3. Motion - George Mills motioned the Board to award the Bid Package #1 contract for Excavation and Concrete to Granger Construction in the not -to -exceed amount of $ 1,824,000. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #3 contract for Structural Steel to Douglas Steel Fabricating for the base bid of $ 1,898,266 plus an additional $ 3,898. (as recommended by Jay Desai, structural engineer, for additional work as mandated in subsequent bid addendas) . The total contract is a not -to - exceed $ 1,902,164. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. George Mills informed the Board that the Committee had also met to discuss the Clark recommendation on awarding a contract to a company for testing welds and concrete. This expense is not a part of the Clark contract and will be contracted with TIFA separately. Of the four bidders, two companies do not maintain equipment necessary to complete the investigation. For that reason, they were not considered qualified bidders. Clark Construction recommended that Testing Engineers and Consultants be awarded the contract for a not -to -exceed $ 47,760. but that Board appropriate a total of $ 60,000 should additional testing become necessary. Motion - George Mills motioned the Board to award the testing contract to Testing Engineers and Consultants for a not -to -exceed amount of $ 47,760. with a total appropriation of $ 60,000 if additional testing becomes necessary. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Emerson Ohl asked that the meeting minutes reflect the following Bid Package numbers and their indentification. Bid Package # 1 - Excavation and Concrete Bid Package # 2 - Selective Demolition Bid Package # 3 - Structural Steel Bid Package # 4 - Masonry and Stone Bid Package # 5 - Miscellaneous Metals Bid Package # 6 - Carpentry Bid Package ## 7 - Metal Siding & Insulated Metal Wall Panels Bid Package # 8 - Roofing and Sheet Metal Bid Package # 9 - Glass Wall Systems, Entrances, Glass and Glazing Bid Package # 10 - Drywall, Metal Studs, Insulation and Fireproofing Bid Package # 11 - Operable Walls Bid Package # 12 - Painting and Wall Covering Bid Package # 13 - Floor Coverings, Terrazzo, Ceramic Tile Bid Package # 14 - Food service Equipment Bid Package # 15 - Elevators Bid Package ,# 16 - Loading Dock Equipment Bid Package # 17 - Mechanical, HVAC, Temperature Controls., Plumbing Bid Package # 18 - Fire Protection Bid Package # 19 - Electrical Pre -Bid meetings will be held on the above referenced Bid Packages next week at the Lansing Center. City of Lansij.-ig-'. Department of Human Relations will be in attendance to instruct all bidders on the.applicable City of Lansingas Wage Determination rates. Bid openings on the above referenced Bid Packages will be he�:J d on Tuesday, January 26, 1993 and Thursday, January 28, .993. The TIFA Committee and the TIFA Board have asked ClarJy Construction to instruct their contractors to save and replant as many trees/bushes from the Michigan Avenue side cf the property as possible. 3) OTHER BUSINESS No motions. 4) PUBLIC COMMENTS None. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 1 ,41_5 Minutes by P. Cook and B. Foreman Emerson B. Ohl ✓ U , �� TIFA Secretary TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING BOARD OF DIRECTOR'S MEETING 9TH FLOOR CONFERENCE ROOM, LANSING CITY HALL WEDNESDAY, FEBRUARY 3, 1993 4:15 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Pe"o_<":. William Porter, Jr.; James Crawford; George Mills MEMBERS ABSENT: Gerald Lett; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Dale Brzezinski; Ken Peterie Chairman Lucile Belen brought the meeting to order at 4:11 1) APPROVAL OF THE JANUARY 6, 1993 BOARD OF DIRECT'OR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the January 6, 1993 Board Director's Meeting Minutes as printed and place them on file. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. 2) SECRETARY'S REPORT A) Lansing Center Update TIFA Committee Chairman George Mills informed the Board that the Committee had met and discussed the recommendations froi7a Clark Construction on the lowest qualified bidder for the following bid packages: Bid Package # 2 - Selective Demolition Bid Package # 4 - Masonry and Stone Bid Package # 6 - Carpentry Bid Package # 7 - Metal Siding/Insulated Metal 'Wall Panels Bid Package # 9 - Glass Wall Systems/Entrances/Glass/Glazii.u:;1 It.was the Committee's recommendation to the TIFA Board to support Clark's recommendation of awarding contracts to the following lowest qualified bidder on the above bid packages. Motion - George Mills motioned the Board to award the Bid Package #2 contract for Selective Demolition to Bierlein Demolition Contractors in the not -to -exceed amount of $ 340,017.00. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #4 contract for Masonry & Stone to Kennedy Masonry in the not -to -exceed amount of $ 1, 168, 200. 00. James Crawford seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #6 contract for Carpentry to Irish Construction in the not -to -exceed amount of $ 687,000.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #7 contract for Metal Siding and Insulated Metal Wall Panels to Architectural Building Products in the not -to -exceed amount of $ 881684.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #9 contract for Glass Wall Systems, Entrances, Glass and Glazing to Metal Building Specialties in the not -to -exceed amount of $ 948,614.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. TIFA Committee Chairman George Mills informed the Board that the Committee had also previously met and discussed the recommendation from Snell Environmental Group, Inc. on the Bids taken for the Soil Remediation contract. After some further investigation of the lowest qualified bidder, the Committee recommends to the Board the award of the contract as follows: Motion - George Mills motioned the Board to award the Soil Remediation contract to S.F. Raymer Company in the not -to -exceed amount of $ 703,693.00. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Committee Chairman George Mills informed the Board that the staff has received correspondence from the Board of Water & Light indicating a charge of $ 5,700.00 for the removal of street lighting along the Michigan Avenue side of the Lansing Center and a re -installation charge of $ 10,100.00 for the lighting to be replaced following construction. The Committee recommends a change order approval in the amount of a not -to -exceed $ 15,800.00 for these changes. Motion - William Porter, Jr. motioned the Board to approve a change order in the amount of $ 15,800 for the removal and re -installation of the lighting along Michigan Avenue. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. Emerson Ohl reviewed "Amendment Two" of the Hobbs & Black architectural contract (as per City Council resolution to provide Schematic Design for Phase III) with the Board. The contract was approved for "schematic design services" only as follows: Motion - William Porter, Jr. motioned the Board to approve the "Amendment T�vo" as an Addendum to the Hobbs & Black Associates, Inc. contract dated March 27, 1992. This addendum is for Schematic Design Services only for Phase III in the not -to -exceed amount of $ 108,500.00. George Mills seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills Motion carried. 3 ) OTHER BUSINESS No motions. 4) PUBLIC COMMENTS Dale Brzezinski and Ken Peterie representing local labor unions asked questions of the Board on the Soil Remediation bid award. They voiced concerns about an out of town contractor hiring local union workers vs. non union workers and not paying prevailing wages. The Board responded to their questions and assured them that there are some strict guidelines in place to keep watchful eye over payment of prevailing wages on this project. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 4:50 p.m. Minutes by P. Cook �J Emerson B. Ohl TIFA Secretary 03- 1 3-94;11 0 : 0 RC1/D TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING 9TH FLOOR CONFERENCE ROOM, LANSING CITY HALL FRIDAY, FEBRUARY 26, 1993 11:00 A.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Ken Lawless; Bob Smith Chairman Lucile Belen brought the meeting to order at 11:00 a.m. 1) APPROVAL OF THE FEBRUARY 3, 1993 BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the February 3, 1993 Board of Director's Meeting Minutes as printed and place them on file. George Mills seconded the motion. YEAS: .Belen; Haar; Petroff; Porter; Mills Motion carried. 2) SECRETARY'S REPORT A) Lansing Center Update TIFA Committee Chairman George Mills informed the Board that the Committee had met and discussed the recommendations from Clark Construction on the lowest qualified bidder for the following bid packages as well as the elimination of some costs from previously awarded bid packages as follows: Bid Package # 4 - Masonry & Stone (previously awarded) Bid Package # 5 - Miscellaneous Metals Bid Package # 8 - Roofing Bid Package #10 - Drywall & Metal Studs Bid Package #13 - Flooring Bid Package #15 - Elevators Bid Package #16 - Loading Dock Equipment Bid Package ##17 - Mechanical Bid Backage #18 - Fire Protection Bid Package #19 - Electrical It was the Committee's recommendation to the TIFA Board to support both Clark's recommendation of awarding contracts to the following lowest qualified bidder on the above bid packages as well as Hobbs & Black's concurrence on the elimination of costs associated with previously awarded bid packages. Motion - George Mills motioned the Board to delete the anti -graffiti sealant from both outside and inside walls for a cost savings of $ 112, 000.00 to previously awarded Bid Package #4 - Masonry and Stone. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #5 contract for Miscellaneous Metals to Davis Ironworks in the not -to -exceed amount of $ 254,000.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #8 contract for Roofing to Bruno - Martin Company in the not -to -exceed amount of $ 256,668.00, which includes the cost savings of $ 18,290.00 as recommended by' the elimination of gysum on the deck as well as additional layers of insulation. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #10 contract for Drywall and Metal Studs to the William Reichenbach Company in the not -to -exceed amount of $ 1,546,355.00, which includes a $ 9,200.00 credit for a change from baffled ceiling to acoustical ceiling in the lounge area. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #13 contract for Flooring to Lansing Tile in the not -to -exceed amount of $ 418,708.00, which includes a $ 19,302.00 cost savings for elimination of terrazzo tile in some building areas. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #15 contract for Elevators to Otis Elevator in the not -to -exceed amount of $ 178,400.00, which includes.a $ 1,000.00 additional charge for 8' doors vs 7' doors. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills -motioned the Board to award the Bid Package #16 contract for Loading Dock Equipment to Overhead Door of Lansing in the not -to -exceed amount of $ 8,550.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package 10117 & Bid Package #18 contracts for Mechanical and Fire Protection to John E. Green Company in the not -to -exceed amount of $ 2,839,100.00 which includes a $ 201,900.00 credit for awarding the packages combined as well as deleting some additional items as recommended by Clark and approved by Hobbs and Black. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package # 19 contract for Electrical to Quality Electric in the not -to -exceed amount of $ 1,581,980.00 which includes a $ 28,000.00 credit for changes in wiring and conduit from original specs. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve �A change order in the amount of $ 6,309.00 to Adams Advertising for the removal and relocation of the Lansing Center sign from Michigan Avenue to Cedar Street. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve a change order in the not -to -exceed amount of $ 13,800.00 for the enlarging of elevator r for moving staging and set-up equipment between the lower and upper building level. John Petroff seconded the -motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. TIFA Committee Chairman George Mills made an inquiry to staff about receipt of a previously requested inventory from the Lansing Center management. Upon hearing this request has not been received, Chairman Mills asked that TIFA staff prepare another letter of correspondence directed to GLCEA Building Committee members making a "second request" for a complete inventory of the furniture, fixtures and equipment at the: Lansing Center and stressing the urgency of the request to enable our design consultant to complete ordering new furniture in time for the projects completion. TIFA Committee Chairman George Mills recommended the TIFA staff prepare a letter of correspondence to Mayor Crawford inquiring about his knowledge that the GLCEA was considering entering into a long term contract with a private caterer for the new kitchen. The Committee recommends that no long term contract be entered into prior to a decision on the possible "privatization" matter being resolved. Committee Chairman George Mills informed the Board that the staff has received correspondence from the Board of Water & Light in response to questions regarding consideration of two alternative eletrical service proposals for the Lansing Center expansion. Chairman Mills requested TIFA staff preparr_: a letter of explanation addressing both proposals and asked staff to also set a meeting with GLCEA Building Committee and TIFA Committee members to discuss this issue. Emerson Ohl informed the Board that earlier this week he and other staff personnel had met with Snell Environmental Group, Inc. staff at SEG's request to discuss the overages that had occurred regarding SEG's not to exceed contract for bidding preparation, recommendation and construction oversight work. Emerson indicated that SEG has asked to meet with the TIFA Committee regarding these fee overages and Chairman Mills responsed by requesting staff to set a meeting with both groups to listen to SEG's concerns. 3) OTHER BUSINESS No motions. 4) PUBLIC COMMENTS None. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 12:37 p.m. Minutes by P. Cook Emerson B. Ohl TIFA Secretary 10 0 TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING 9TH FLOOR CONFERENCE ROOM, LANSING CITY HALL FRIDAY, MARCH 26, 1993 11:00 A.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills; Joseph Pandy, Jr. MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT:. Cora Huguely; Ken Lawless; Harold Leeman Chairman Lucile Belen brought the meeting to order at 11:53 a.m. 1) APPROVAL OF THE FEBRUARY 26, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the February 26, 1993 Special Board of Director's Meeting Minutes as printed and place them on file. George Mills seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills; Pandy- Motion andy Motion carried. 2) SECRETARY'S REPORT A) Lansing Center Update TIFA Committee Chairman George Mills informed the Board that the Committee had met and discussed the recommendations from Clark Construction on the lowest qualified bidder for the following bid packages: Bid Package # 11 - Operable Walls Bid Package # 20 - Asphalt Paving, Sidewalks, Curbs, Gutters and Seeding It was the Committee's recommendation to the TIFA Board to support both Clark's recommendation of awarding contracts to the following lowest qualified bidder on the above bid packages as well as approval of some unanticipated construction costs. Joseph Pandy, Jr. left the meeting at 12:02 p.m. Motion - George Mills motioned the Board to recommend the TIFA Chair write a letter to the Mayor asking him to correspond with the Convention Authority about not entering into any long term leases/contracts until the issues regarding "changes of mission, marketing and operations", (as directed by the City Council resolution of 9/28/92) are resolved. The motion further recommended the TIFA Committee review this letter before its mailing. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. Motion - George Mills motioned the Board to approve a not -to -exceed expenditure of $ 30,000.00 to reroute existing sewer drains around the overpinning area (foundations). William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve a not -to -exceed fee of $ 4,800.00 to Clark Construction for a cost estimate of Phase III (as directed by Council resolution). Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package #11 contract for Operable Walls to Commercial Door Systems in the not -to -exceed amount of $ 329,555.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to award the Bid Package # 20 contract for Asphalt Paving, Sidewalks, Curbs, Gutters & Seeding to Eastlund Concrete in the not -to -exceed amount of $ 126,440.00. William Porter, Jr.'seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve Change Order Request #1 in the amount of $ 8,487.00 for miscellaneous unexpected construction costs/credits (as attached). Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Mills NAYS: Porter Motion carried. Motion = George Mills motioned the Board to approve the TIFA Committee's recommendation that no new stairway be built on the east end of the existing pedway.. William Porter, Jr. seconded. Much discussion surrounding security issues, pedestrian traffic and insurance liability for the Center ensued, and the motion was tabled until a future meeting to enable Mrs. Huguely time to discuss TIFA's position on this with the Authority Board. Motion - George Mills motioned the Board to approve the TIFA Committee's recommendation that the new switchgear equipment for the Lansing Center be provided by Quality Electric, not Board of Water & Light. (This is not an additional cost, the price was included in the electrical bid package). John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve the expenditure of $ 400.00/month for rental of trailer to house the Lansing Center administra- tion staff during construction. John Petroff- seconded etroffseconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Motion - George Mills motioned the Board to approve the TIFA Staff contact Dickinson, Wright, et. al., for a review of the SEG contracts TIFA entere6 into, in light of the fact that there have been issues brought to the TIFA Committee by SEG on the amount of their contract and what they perceive as additional scope of work provided. Motion amended to include review with legal counsel on issues raised by HUFCOR (Bid Package # 11 - Operable Walls) regarding their intention to file a bid protest form over their displeasure at not being awarded the contract. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 3) OTHER BUSINESS No motions. 4) PUBLIC COMMENTS Cora Huguely presented the TIFA Board.with a list of concerns regarding the construction project. She asked that 'the TIFA Board be open to a number of issues presented in this letter. TIFA Committee Chairman Mills indicated that her concersss would be discussed at the next Committee meetinct. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 12:46 p.m. Minutes by P. Cook _. Emerson B. Ohl TIFA Secretary ( �-1 -� elA�_O _ ;. RCvID TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING BOARD OF DIRECTOR'S MEETING 9TH FLOOR CONFERENCE ROOM, LANSING CITY HALL WEDNESDAY, APRIL 7, 1993 4:00 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; James Crawford; George Mills; Joseph Reid MEMBERS ABSENT: Gerald Lett; Joseph Pandy, Jr. STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: William Coultas; Cora Huguely; Ken Lawless; Harold Leeman; Rich McNulty; Bill Meiers; Chuck Miller Chairman Lucile Belen brought the meeting to order at 4:03 p.m. 1) APPROVAL OF THE MARCH 26, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the March 26, 1993 Special Board oil` Director's Meeting Minutes as printed and place them on file. John Petroff seconded the motion. Hearing no objections to the motion, the chair ordered the meeting minutes placed on file. 2) SECRETARY'S AND COMMITTEE'S REPORT A) Presentation of Schematic Design - Phase III Bill Meiers of Hobbs & Black presented the schematic design; for Phase III of the Lansing Center expansion. It includes a 50,000 square foot expansion of the exhibition hall, pre - function areas, eletrical/mechanical areas, additional concession areas within the exhibit hall space and a pedestrian exit to the north of the ex -hall. James Crawford entered meeting at 4:16 p.m. It was suggested that one of the additional concession areas be moved to the north to accommodate multiple rentals of the exhibit_ hall space. It was also suggested that a modification to the design be made to accommodate additional restrooms as those shown under Phase II are not believed to be adequate with the additional space projected under Phase III. Also a review of the limited pre -function area in the north corridor will be discussed to expand space if architecturally able. George Mills entered meeting at 4:40 p.m. Bill Meiers indicated he would consult with Richard Black and have a re -design of the schematic drawings, incorporating these suggestions within a weeks period of time to allow TIFA to forward to the City Council for their consideration. It was also recommended that a revision of Clark's presented estimated cost of construction, to reflect a more accurate cost incorporating suggested alterations, be made before any presentation to the City Council is undertaken. James Crawford left the meeting at 4:45 p.m. B) Approval of Contracts TIFA Committee Chairman George Mills informed the Board that the Committee had met and discussed the recommendations from Clark Construction on the lowest qualified bidder for the following bid packages: Bid Package # 5 B - Ornamental Metals Bid Package # 21 - Landscaping & Irrigation It was the Committee's recommendation to the TIFA Board to support both Clark's recommendation of awarding contracts to the following lowest qualified bidder on the above bid packages as well as approval of an unanticipated construction cost. Motion - George Mills motioned the Board to approve a pre -payment expenditure of $ 11,894.00 'to Consumer's Power Company to install additional gas service to the new kitchen area at the Lansing Center. Kathryn Haar seconded -the. motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the Board to award the Bid Package #5B contract for Ornamental Metals to Couturier Iron Craft in the not -to - exceed amount of $ 445,333.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the Board to award the Bid Package # 21 contract for Landscaping to Moore-Trosper Construction in the not -to -exceed amount of $ 192,602.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. James Crawford re-entered the meeting at 4:55 p.m. Committee Chairman Mills addressed the Board with a list of construction concerns presented by Cora Huguely at the last Board meeting on 3/26/93. The following represents the TIFA Boards recommendation on each of the items presented: Item #1) better customer relations by construction workers - addressed on a weekly basis at progress meetings Item #2) pedway issue - Mrs. Huguely will respond to TIFA Staff prior to the next Board meeting re: insurance, liability issues, maintanance, security, etc. Item #3) stairway from public parking 'lot - TIFA Committee believes this is not a critical piece of construction project Item #4) eliminate planters from main concourse - design consultant has included these as a method to scale 40' walls down to human level; Hobbs & Black recommends keeping planter as is and TIFA Committee agrees they should remain Item #5) administrative restroom - Committee believes this is not an essential item to the project; Mrs. Huguely will need to present a request from the total Authority authorizing their commitment to pay for all costs associated with the architectural, engineering and construction fees of a restroom in the administrative offices. When this written commitment is received, the TIFA Board will take action on this matter. James Crawford left meeting at 5:10 p.m. Item #6) utility load costs due to construction - addressed with Board of Water & Light staff Item #7) Authority overseeing FF&E purchases - TIFA Board has a design consultant who will recommend FF&E items to TIFA Board for their approval; Authority will have a chance to respond to consultant's recommendation Item #8) completion dates for kitchen/meeting rooms/offices - Clark Construction should be consulted to determine completion dates Item #9) clearer floor plans - Hobbs/Black has provided to Cora Item #10) large sign for Michigan Avenue - in place as of today 3) OTHER BUSINESS Emerson Ohl informed Board of current standing relating to State tax proposals that would effect future bonding for a Phase III project. Development/financial plans would need to be completed and approved by the City Council prior to July 1, 1993 with bonds sold and a closing prior to October 1, 1993. DNR has given preliminary approval of $ 2 Million Site reclamation grant predicated upon the City's commitment to proceed with Phase III of the Lansing Center expansion. George Mills informed the Board regarding issues with Snell Environmental Group. Upon review by our legal counsel, it is recommended that none of Snell's claims for additional costs be paid, all costs are within the scope of the original contract. It was agreed that a written communication be forwarded to Snell so informing them of TIFA's position on their claim and stipulating they proceed to a conclusion as outlined in their contract. 4) PUBLIC COMMENTS None. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 5:28 p.m. Minutes by P. Cook Emerson B. Ohl TIFA Secretary 03 -1u -94A09:3 R C V D TAX INCREMENT FINANCE AUTHORITY - OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING MAYOR'S CONFERENCE ROOM, LANSING CITY HALL WEDNESDAY, MAY 121 1993 4:00 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; James Crawford; George Mills; Joseph Reid MEMBERS ABSENT: Gerald Lett; Joseph Pandy, Jr. STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Gerald Boerner; Ken Lawless; Harold Leeman; Chuck Miller Chairman Lucile Belen brought the meeting to order at 4:02 p.m. 1) APPROVAL OF THE APRIL 7, 1993 BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the April 7, 1993 Board of Director's Meeting Minutes as printed and place them on file. John Petroff seconded the motion. Hearing no objections to the motion, the chair ordered the meeting minutes placed on file. 2) SECRETARY'S AND COMMITTEE'S REPORT A) Approval of Contracts TIFA Committee Chairman George Mills informed the Board that the Committee had met and discussed the recommendations from Clark Construction on the lowest qualified bidder for the following bid packages: Packages m 12, Orl 14, & T 22 It was the Committee's recommendation to the TIFA Board to support Clark's recommendation of awarding contracts to the following lowest qualified bidder on the above listed bid packages as follows: Motion - George Mills motioned the Board to award the Bid Package # 12 contract for Painting and Wall Covering to Genessee Painting Company, Inc. in the not -to -exceed amount of $ 138,100.00. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the.Board to award the Bid Package # 14 contract for Food Service Equipment to Brothers Restaurant Supply in the not -to -exceed amount of $ 658,575.00. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the Board to award the Bid Package # 22 contract for Sound Reinforce- ment System to KLA Laboratories in the base bid amount of $ 480,000.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the Board to approve the transfer of $ 84,800.00 from the F.F. & E. budget to the construction fund account to purchase portable sound equipment through KLA Laboratories (award of Sound System bid). John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Motion - George Mills motioned the Board to approve hiring Coffeen Fricke (Acoustical consultant) to conduct sound system testing and acoustical adjustments through an addition to the Hobbs & Black contract in the NTE amount of $ 72, 800.00 William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. B) Other Construction Items An invoice was received from the GLCEA for the charges associated with the connection of water/sewage to the administrative staff trailer during construction. Motion - George Mills motioned the Board to approve i:1',;., payment of $ 1,339.00 to the John E. Green Company for the connection of water/sewage the trailer provided for Lansing Center admi.i istrative staff during construction. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills ABSTAIN: Reid Motion carried. Ken Lawless and Gerald Boerner presented additional costs associated with Bulletin # 4, # 5 and # 6 to the TIFA Board. A breakdown of these costs were provided each Board member. George Mills informed the Board that the Committee reviewed each of these costs and recommended the Board's approval. Motion - George Mills motioned the Board to approve the additional costs associated with Bulletin rr 4 through Bulletin # 6 with contingency monies as follows: Bulletin # 4 $ 187,028. Overpin costs 55,447. Relocation of storm sewer 19,898. Add reveals to operable walls 371807. Test borings for overpins 3,330. Bulletin # 5(excluding hydrant Mi Ave) 123. Bulletin # 6 24,827. Total additional costs $ 328,460. Total contingency left $ 687,997. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter, Mills NAYS: Reid Motion carried. Jim Crawford entered the meeting at 4:14 p.m. George Mills updated the Board regarding issues with Snell Environmental Group. Upon review by our legal counsel, it is recommended that none of Snell's claims for additional costs be paid, all costs are within the scope of the original contract. On Friday, May 7, 1993 (at TIFA counsel-" 3) 4) 5) recommendation) the TIFA Staff forwarded a check fog $17,940.00 in payment of the 11/13/92 contract entered into with SEG, with the understanding that SEG would terminate iti•. work on the Lansing Center soil remediation as of that date. It was also recommended that a written communication be forwarded to both Clark Construction and S.F. Raymer so informing them of this. Motion - George Mills motioned the Board to approve directing TIFA Staff to draft a letter to Clark Construction Company authorizing them to act on TIFA's behalf for direction and oversight to the S.F. Raymer Company - TIFA' soil remediation contractor. Also motioned was directing TIFA Staff to dire_::. correspondence to S.F. Raymer indicating tha-' SEG is no longer handling construction over- sight on this project and all correspondence and payment requests should be forwarded directly to the TIFA Office. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills ABSTAIN: Reid OTHER BUSINESS A) Selection of FY 192/93 Auditors Motion - Kathryn Haar motioned the Board to approve retaining KPMG Peat Marwick as auditors for TIFA for the FY 192/93 at the same fee as last year - $ 5,000.00. William Porter, J�, seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Crawford; Mills; Reid PUBLIC COMMENTS None. ADJOURNMENT Motion carried. Chairman Belen declared the meeting adjourned at 4:19 p.m. Minutes by P. Cook Emerson B. Ohl TIFA Secretary ;CVD TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING MICHIGAN ROOM I - LANSING RADISSON HOTEL THURSDAY, MAY 27, 1993 11:00 A.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; James Crawford; Gerald Lett; George Mills; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Dave Berridge; Bob Clegg; Ken Lawless; Doug Rubley; Bob Smith; Jud Werbelow Chairman Lucile Belen brought the meeting to order at 11:07 a.m. 1) APPROVAL OF THE MAY 12, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES No action was taken on the minutes. They will be brought up at the next Board meeting. 2) SECRETARY'S REPORT A) Third Amended Development & Financing Plans Phase III Lansing Convention/Exhibition Center and Associated Facilities and Parking System Project Bob Clegg, Dave Berridge and Doug Rubley made a presentation to the Board showing them the Parking System structures background; information on LBA's purchase of property for proposed parking system development along Michigan/Cedar/Larch; current/future parking system revenues/debt; capacity to meet major portion of current/future parking system debt with Phase III TIFA bonds. The Third Amended plan is flexible and proposes all of the following, but does not commit TIFA to bond for each of the individual projects named: 1) Defeasance of 1992 Phase II bonds - $ 25,000,000 2) Acquisition/lease of all/portion of parking system by the TIFA - $ 41,000,000 3) Completion of Lansing Center Phase III - $ 20,000,000 TIFA Board Members asked questions of the presenters. Following some discussion on the issues, the following motions were made: MOTION - James Crawford motioned the Board to approve the resolution set before them, approving the Third Amended Development Plan and Third Amended Tax Increment Financing Plan (Phase III Lansing Convention/Exhibition Center and Associated Facilities and Parking System Project). Gerald Lett seconded the motion. More discussion from Board Members ensued regarding both the Development & Financing Plans and: CALLED FOR THE QUESTION: Jim Crawford called for the question. YEAS: Belen; Haar; Petroff; Crawford; Lett; Mills; Pandy; Reid NAYS: Porter YEAS: Belen; Haar; Petroff; Porter; Crawford; Lett; Mills; Pandy; Reid Motion carried. 3) OTHER BUSINESS None. 4) PUBLIC COMMENTS None. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 12:20 p.m. Minutes by P. Cook Emerson B. Ohl TIFA Secretary -1 94AI I 3C [;CVD TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING FIREPLACE ROOM - UNIVERSITY CLUB AT M.S.U. THURSDAY, JULY 1, 1993 11:00 A.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr. ; Gerald Lett; George Mills MEMBERS ABSENT: James Crawford; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Ken Lawless Chairman Lucile Belen brought the meeting to order at 11:08 a.m. Chairman Belen thanked the Board for attending this meeting on such short notice as well as meeting at an alternative place. She told the Board that the Conference rooms usually available to the Board were all in use and that meant meeting outside of City Hall. 1) APPROVAL OF THE 14AY 12, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES 2) APPROVAL OF THE MAY 27, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - George Mills motioned the Board to accept the meeting minutes from both the May 12, 1993 and May 27, 1993 Special Board of Director's Meetings as presented and place them on file. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 3) SECRETARY'S & COMMITTEE'S REPORT A) Soil Remediation Contract 1) Change Order (S.F. Raymer) - $ 16,592.70 Ken Lawless explained Change Order # 1 to the S.F. Raymer Soil Remediation Contract. This change order would increase the contract by $ 16,592.70 with both deducts for portions of the contract that were changed (overpins) as well as adds to the contract for additional services provided (storm sewer relocation). Motion - George Mills motioned the Board to approve Change Order #1 in the amount of $ 16,592.70 to increase the S.F. Raymer remediation contract. The motion was seconded by Kathryn Haar. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 2) Backfill at Lower Level Kitchen Receiving Area Ken Lawless presented the Board with a written recommendation to contract to Granger Construction for an additional $ 19,487.00 to provide approximately 2,000 yds of backfill at the lower level kitchen receiving area to bring to grade. Ken indicated that Clark was withdrawing their previous recommendation to award this addition to S.F. Raymer based on a further study that Raymer's quote was a unit price and could possibly exceed the firm price for the entire additional work provided by Granger. Motion - George Mills motioned the Board to approve an addition to the Granger contract in the amount of $ 19,487.00 for additional services provided in backfilling the lower level kitchen receiving area to grade. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Ken Lawless indicated the possible need for further testing of soils in a few specific areas at the Lansing Center. He reported to the Board that he felt the costs involved would be minimal, but asked for their concurrence to provide these as needed. Motion - George Mills motioned the Board to approve additional soil testing (should it become necessary) at the Lansing Center. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. B) Clark Construction 1) Bulletin # 7 and # 8 - $ 7,803.00 Ken Lawless reviewed Bulletin # 7 & # 8 with the TIFA Board. It is Clark's recommendation that a change order be issued for a total contract add of $ 7,803. 00 (per attached summary) . Motion - George Mills motioned the Board to approve a Change Order to the Clark Construction contract in the not -to exceed amount of $ 7,803.00 for miscellaneous extras and Bulletins #7 & #8 as presented. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. Gerald Lett entered the meeting at 11:29 a.m. C) Pedway Exit/Elevator Emerson Ohl reviewed the Pedway Exit - Budget presented 'Co each TIFA Board member. He informed the Board that much discussion has taken place with the Mayor and other City departments relating to this important issue. The A.D.A. has written the Mayor indicating that since the stairway and elevator (existing prior to construction) in the Lansing Center lobby has been removed with the current design of Phase II, that any after hours pedestrians (specifically handicappers) lose access to the parking area below the Lansing Center. The A.D.A. believes it has an arguable case to mandate the construction of a new elevator/stairway exit from the east end of the Pedway. After much discussion by the Board relating to both the necessity for construction of this new exit as well as the sizable monetary cost to construct, the following motion was made: Motion - John Petroff motioned the Board to approve the construction of an elevator and stairway at the East end of the Pedway. The motion was amended to include having Clark & Hobbs/Black checking into additional alternatives that could shave some of the costs associated with this construction. Gerald Lett seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Lett; Mills Motion carried. D) Lansing Center Expansion Study Emerson Ohl reviewed the agreement presented to the Board outlining the services to be provided by Public Sector Consultants to study the following: 1) Economic effects of expanding the Lansing Center's Exhibition space; 2) Options for financing expansion; 3) Alternative forms of management for the Center. The TIFA has been requested to financially support this study. An invoice for $ 8,250.00 for 1/2 of TIFA's support has been received. The other organizations contributing to this study are: Lansing 2000; C/VB; GLCEA; Chamber of Commerce. Motion - William Porter, Jr. motioned the Board to approve payment of this invoice in the not -to -exceed amount of $8,250.00 towards the Public Sector Consultants expansion study. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Lett; Mills Motion carried. E) Third Amended Development & Financing Plans - Phase III Lansing Convention/Exhibition Center and Associated Facilities and Parking System Project (Update) Emerson reviewed with the Board their previous approval of both the Development & Financing Plans at last month's TIFA board meeting. The Board discussed some additional questions they had relating to management/operations of the parking system and possible privatization of the system. All Board members present agreed that there will not be enough revenues to do all three plans (defease 192 TIFA bond; Phase III of Lansing Center; parking system project). Those Board members present all felt that TIFA's relieving the parking system of its debt alone is not the answer to the existing problems. Emerson also reviewed the cash balances in both the Bond "Construction Costs" account as well as the TIFA reserve revenue (TIFA revenues minus debt service) account. It appears as if we will have some monies remaining out of both the current bond and reserve account to expand a small portion of the Exhibit Hall. Each additional exhibit hall bay (6,300 square feet) has a cost of $1.5 million each bay. (without any monies set aside for contamination or f.f. & e.) Emerson also reminded that the original bids were taken with the small addition of exhibit hall space (to net 50,000 sq. ft.) on the north end, as an Alternate #1. Two of these alternate bids were asked to extend their firm bid for an additional 30 days (past 180 days). These two bids expire on July 6, 1993. Most of the other bids expire during July and August, 1993. As it is imperative that coordination of construction for any additional exhibit hall space be carefully designed and planned during the current phase of construction, it is necessary for the TIFA Board to take 3) 4) 5) action on the amount of additional space to construct, given the current projection of TIFA monies that might be available if future additional costs of current construction are kept in check. The Board was given the following information relative to square footage for each additional bay constructed: With Alternate # 1 (net 50,400 square feet) 1 Additional Bay (net 56,700 square feet) 2 Additional Bays (net 63,000 square feet) 3 Additional Bays (net 69,300 square feet) 3 Additional Bays plus 1/2 bay (net 72,450 square feet) Given these alternatives, the Board was reminded tha":C, Alternate #1 is included in the current costs of construction, only the additional bays will cost approximately $ 1.5 Millioia more for each bay. After further discussion regarding the estimate of cash on hand relative to funding any additional exhibition hall space, the following motion was made: Motion - George Mills motioned the Board to approve authorizing Hobbs & Black on the Design Development of three (3) additional bays of exhibition hall space (in addition to Alternate #1 space) with 30 foot ceilings (vs. current 40 foot). The motion was amended to include an alternate 1/2 bay of space at the northern end of the exhibition hall. The motion included authorization of Clark Construction as Project Manager for this additional phase of construction., William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Lett; Mila.� OTHER BUSINESS No motions made. PUBLIC COMMENTS None. ADJOURNMENT Motion carried. Chairman Belen declared the meeting adjourned at 12:52 p.m. Minutes by P. Cook ;kp*k-6�z Emerson B. Ohl TIFA Secretary 03-]0-94A09:3U" RCVD TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING STATE ROOM III - RADISSON HOTEL TUESDAY, AUGUST 24, 1993 11:00 A.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills ; Joseph Pandy, Jr. MEMBERS ABSENT: James Crawford; Gerald Lett Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Gerald Boerner; Tom Galyon; Ken Lawless; Kevin McKinney; Chuck Miller; Bob Smith Chairman Lucile Belen brought the meeting to order at 11:40 a.m. 1) APPROVAL OF THE JULY 1, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the meeting minutes from the July 1, 1993 Special Board of Director's Meeting as printed and place them on file. George Mills seconded the motion. Hearing no objection from any Board member, Chairman Belen so ordered the minutes approved and placed on file. YEAS: Belen; Haar; Petroff; Porter; Mills; Pandy Motion carried. 2) SECRETARY'S & COMMITTEE'S REPORT A) Soil Remediation Contract 1) Change Order (S.F. Raymer) - $ 2,603.00 Ken Lawless explained Change Order # 2 to the S.F. Raymer Soil Remediation Contract. This change order would increase the contract by $ 2,603.00 for additional services provided in excavating hidden loose concrete and excavation for the sanitary sewer. Motion - George Mills motioned the Board to approve Change Order 702 in the amount of $ 2,603.00 to increase the S.F. Raymer remediation contract. The motion was seconded by Kathryn Haar. YEAS: Belen; Haar; Petroff; Porter; Mills; Pandy Motion carried. B) Impact of SB 1 on Tax Increment Financing Emerson presented the Board with correspondence from Jim Kiefer, Dykema Gossett, regarding their opinion/concerns of the impact SB 1 has had on tax increment financing authorities with current/future projects. He further explained that approximately 65% of our TIF revenue is from school taxes and without that revenue, the TIFA will be unable to meet its bond debt service payments - the City will be responsible for meeting existing debt payments to bondholders. Kevin McKinney reviewed with the Board that while the legislature is sympathetic with the communities that are struggling to figure out how to meet bond obligations, in his opinion it is likely the state will grandfather those projects with current debt obligations. Projects that are in the works for future bonding will be discussed individually with the state treasury. At the last TIFA Board meeting, Emerson discussed with Board members that we currently have funds available to finance a small expansion to the Exhibition hall. With funds from TIF excess revenue (captured taxes [-] debt service) plus monies from current bond issue, we can afford an expansion that will net approximately 72,450 square feet of exhibit space. Tom Galyon relayed to the Board that the C/VB is currently marketing up to 72,000 square feet of space (anticipating that the additional expansion will take place in the future). After much discussion and confirmation from the TIFA Staff that funds are on hand to proceed with this expansion, the following motion was offered: Motion - William Porter, Jr. motioned the Board to proceed with the expansion of the Exhibit Hall to net 72,450 square feet of space. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills; Pandy Motion carried. C) Third Amended Development & Financing Plans - Phase III Lansing Convention/Exhibition Center and Associated Facilities and Parking System Project (City Council modifications to Plans) Emerson reviewed with the Board their previous approval both the Financing and Development Plans - Phase III. He reviewed the resolution, in the TIFA Board packets, that included some modifications in "Exhibit All of the resolution. The Council has directed the TIFA to prioritize potential activities under these plans - only after the activities have been reviewed by Council and Council has provided their comments/recommendations/advice. Secondly, providing a statement regarding the City's ability to pledge its good faith and credit to support the Authority's bonds - if a majority vote of the Council approves such a pledge. Emerson also indicated that their is a general feeling of doubt regarding the State's willingness to approve any future TIFA plans, since the passage of SB 1. Further, he told the Board that in reviewing the LBA's official statement on the parking system bonds, it was noticed that about $ 20 million in bonds cannot be redeemed without penalty and the remaining $ 10 million in bonds are zero coupon bonds, having a balloon at the end of the 20 year amortization. 3) OTHER BUSINESS No motions made. 4) PUBLIC COMMENTS None. 5) ADJOURNMENT Chairman Belen declared the meeting a journed at 12:03 p.m. Minutes by P. Cook :(G(l_ Emerson B. Ohl TIFA Secretary 03-1`11-94A09:-5� RC'l, TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING BOARD OF DIRECTOR'S MEETING LANSING CENTER - LANSING ROOM II WEDNESDAY, OCTOBER 6, 1993 4:00 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Cora Huguely; Ken Lawless; Bob Smith Chairman Lucile Belen brought the meeting to order at 4:0.2 p.m. 1) 2) APPROVAL OF THE AUGUST 24, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the meeting minutes from the August 24, 1993 Special Board of Director's Meeting as printed and place them on file. George Mills seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. SECRETARY'S & COMMITTEE'S REPORT A) Change Order - S. F. Raymer Company ($ 19,600.75) B) Change Order - Clark Construction $ 32,225.00 C) Change Order - Clark Construction $ 25,882.00 D) Change Order - Clark Construction $ 28,787.00 E) Change Order - Clark Construction $ 34,000.00 George Mills informed the Board that the TIFA Committee had reviewed each of these change orders and felt they were reasonable and in order. Motion - George Mills motioned the Board to approve Change Order A through E in the not -to -exceed amounts specified above. The motion was seconded by William Porter, Jr. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. F) Furniture, Fixtures & Equipment Budget George Mills reviewed with the Board the F F & E budgeted items in the amount of $ 680,160.93. He indicated that this figure should be used as an estimate for bidding purposes, and he opened up the question to discussion. Motion - George Mills motioned the Board to authorize Hobbs & Black to proceed with preparation of bidding documents for the approved furnishings and equipment.. He further motioned that the figure of $ 680,160.93 presented will be used as an estimate for bidding purposes. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 3) OTHER BUSINESS Emerson presented the Board with a copy of the promotional piece being used by the Convention/Visitor's Bureau when they market space at the expanded Lansing Center. Emerson reviewed correspondence indicating that KLA Laboratories would begin preparations to install new sound equipment in the existing Exhibit Hall within a few weeks. The new system should be completed no later than mid January, 1994. 4) PUBLIC COMMENTS Cora Huguely asked the Board if they had reconsidered their position on the addition of another restroom in "Exhibit Hall C". Bob Smith responded that the current number of restrooms designed in the expanded Center exceeds the number required by Code. Cora agreed that perhaps Bob's assessment is correct, but feels that the Board should be sensitive to the specific problems that an inadequate number of restrooms would play in determining the success of conventions/meetings, etc. at the Center. Cora was told that the Committee had considered her proposal and would not be designing an additional restroom near or adjacent to Exhibit Hall C. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 4:26 p.m. to tour the Lansing Center construction in progress. Minutes by P. Cook Emerson B. Ohl, TIFA Secretary I\'CVD TAX INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING RADISSON HOTEL - STATEROOM I Thursday, November 18, 1993 12:00 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Cora Huguely; Ken Lawless; Bob Smith Chairman Lucile Belen brought the meeting to order at 12:10 p.m. 1) APPROVAL OF THE OCTOBER 6, 1993 BOARD OF DIRECTOR'S MEETING MINUTES Motion - John Petroff motioned the Board to approve the meeting minutes from the October 6, 1993 Board of Director's Meeting as printed and place them on file. George Mills seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 2) SECRETARY'S & COMMITTEE'S REPORT A) Change Order - Clark Construction - $ 15,689.00 B) Change Order - Clark Construction - $ 20,270.00 C) Change Order - Clark Construction - $ 18,739.00 D) Change Order - Clark Construction - $ 3,418.48 E) Change Order - Clark Construction - $ 18,158.00 George Mills informed the Board that the TIFA Committee ha(: reviewed each of these change orders and felt they were reasonable and in order. Motion - George Mills motioned the Board to approve Change Order A through E in the not -to -exceed amounts specified above. The motion was seconded by John Petroff. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. The Board discussed the Committee's recommendation for an increase in after hours security at the construction site, due to the fire started a few weeks ago which destroyed a few new exterior doors. Ken Lawless has been checking on the costs for hiring additional security and will be able to present these costs at the next Board meeting. The Boa.C. also discussed asking Mrs. Huguely to submit a claim and cop_i of the cost to replace the damaged doors to the Insuranc.... agent. Motion - William Porter, Jr. motioned the Board to authorize the TIFA Secretary, Emerson Ohl, to contact the Insurance agent providing the Builder's Risk policy and obtain quotes on the cost of lowering the deductible from $ 5,000.00. The motion also includes the authorization for Mr. Ohl to change the current policy if the costs obtained justify a modification to the existing policy. Joh:f Petroff seconded the motion. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. F) Sound System - Phase II & IIA Ken Lawless informed the Board about recent correspondencs with the sound system contractor relating to modifications necessary to the Phase II sound equipment, should TIFA go ahead with Phase IIA. The Phase IIA system (Exhibit Hall C) is quoted at approximately $ 225,000. The Phase II plans call for modifications to the existing system to take place during mid-December thru January, 1994 (when the sound systeic will not be required by booking groups). Should Phase IIA become a reality, it is important that modifications for that new sound system be incorporated at the same time, versus modifying the equipment a second time. A quote has not yet been received by the sound manufacturer on the cost of making the Phase IIA modifications during this phase. Motion - George Mills motioned the Board 'Co authorize the TIFA Committee to review any additional costs associated with modifying Phase II sound system to a Phase IIA system. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. G) Soil Remediation - Phase IIA After much discussion and review about some of the problems that came to light during the soil remediation of Phase II, the following motion was offered: Motion - George Mills motioned the Board to authorize the TIFA Secretary, Emerson Ohl, to review the Excavation/Concrete specs for Phase IIA with the DNR to ensure compliance on the soil remediation. Kathryn Haar seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 3) OTHER BUSINESS A) Clark Construction - Change Order - $ 12,858.00 Bob Smith reported to the TIFA Board that there is a federal safety requirement that any window that is lower than 18" from the floor, is larger than 9 s.f. and has a walkway on both sides, needs to be built with safety glass or provide for a guardrail. The Uniform code (City of Lansing uses and just included this year, a provision with stipulates that a walkway on only one side of the glass necessitates either safety glass or a guardrail). Bob is recommending the guard- rail as the glass is already installed and would be cost prohibitive to replace. Motion - George Mills motioned the Board to approve a change order in the not -to -exceed amount of $ 12,858.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. 4) PUBLIC COMMENTS Cora Huguely asked the Board to consider a modification to the Administrative Office door to include a window. Bob Smith indicated he would look into it. Emerson informed the Board that they should be receiving invitations to the Convention/Visitor's Bureau Holiday Open House on Friday, December 3, 1993. If any Board member does not receive an invitation this week, they should contact the TIFA Staff. Emerson also informed the Board that just prior to today's meeting, he and Bob Smith had a meeting with the DNR regarding the stairs/exit to be constructed on the east end of the existing pedway. It appears that the new stairs/elevator would be constructed in the floodplain. Bob Smith sent in a letter requesting a variance to the floodplain permit for this exit, earlier in August. The DNR does not feel that it is wise for this type of structure to be built on this floodplain. The DNR asked about the possibility of moving this exit to a different location - Bob told him that all other possibilities had been explored. The DNR will review all documents regarding this variance and respond to Bob Smith. 5) ADJOURNMENT Chairman Belen declared the meeting adjourned at 1:26 p.m. Minutes by P. Cook�`/ /�/� Emerson B. Ohl, TIFA Secretary 03-10-94A09:3'� RCVD TAY INCREMENT FINANCE AUTHORITY OF THE CITY OF LANSING SPECIAL BOARD OF DIRECTOR'S MEETING University Club, Main Dining Room Tuesday, December 7, 1993 12:00 P.M. MEMBERS PRESENT: Lucile Belen; Kathryn Haar; John Petroff; William Porter, Jr.; George Mills MEMBERS ABSENT: James Crawford; Gerald Lett; Joseph Pandy, Jr.; Joseph Reid STAFF PRESENT: Emerson Ohl; Patricia Cook GUESTS PRESENT: Tom Galyon; Ken Lawless; Jim Matthew; Bob Smith Chairman Lucile Belen brought the meeting to order at 12:05 p.m. 1) 2) APPROVAL OF THE NOVEMBER 18, 1993 SPECIAL BOARD OF DIRECTOR'S MEETING MINUTES Motion - William Porter, Jr. motioned the Board to approve the meeting minutes from the November 18, 1993 Special Board of Director's Meeting as printed and place them on file. George Mills seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. TIFA AUDIT FY '92/93 Jim Matthew reviewed the TIFA Audit with Board members, including the 185 bond defeasance and 192 bond proceeds and answered some questions relating to both. Motion - George Mills motioned the Board to accept the TIFA Audit for FY 192/93 as presented and place a clean copy on file. John Petroff seconded the motion. YEAS: Belen; Haar; Petroff; Porter; Mills Motion carried. 3) SECRETARY'S & COMMITTEE'S REPORT A) Change Order - Clark Construction - $ 10,239.00 B) Change Order - Clark Construction - $ 25,637.00 George Mills informed the Board that the TIFA Committee had reviewed each of these change orders and felt they were reasonable and in order. Motion - YEAS: Motion - YEAS: George Mills motioned the Board to approve Change Order A in the not -to -exceed amount specified above. The motion was seconded by William Porter, Jr. Belen; Haar; Petroff; Porter; Mills Motion carried. George Mills motioned Change Order B in the specified above. The by Kathryn Haar. the Board to approve not -to -exceed amount motion was seconded Belen; Haar; Petroff; Porter; Mills Motion carried. C) Discussion on Soil Remediation - Phase IIA Ken Lawless instructed the Board on the method that would be used for disposal of contaminated soil in Phase IIA. All soil excavated for foundations will be considered contaminated and be required to be hauled to a licensed landfill by the contractor. The Board felt this procedure was reasonable. No motions made. D) Bids on #50 (Foundations & Concrete) E) Bids on #51 (Structural Steel) Motion - George Mills motioned the Board to approve Clark Construction's recommendation for hiring Granger Construction Company for Foundations & Concrete at a not to exceed base bid of $ 1,364,000.00 and hiring Douglas Steel Fabricating Corporation for Structural Steel at a not to exceed base bid of $ 997,400.00. William Porter, Jr. seconded the motion. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. F) Phase IIA Guaranteed Maximum Cost Ken Lawless presented the Board with a letter outlining the guaranteed maximum price to construct Phase IIA. With Alternate #1 being included in the cost estimate of Phase II, the cost to construct that portion can be deducted from the total gmp of Phase IIA for a revised total of $ 5,423,961.00. Motion - George Mills motioned the Board to enter into a contract with Clark Construction Company for the construction of Phase IIA (which includes 28,000 square feet of exhibit hall space) for a guaranteed maximum price of $ 5,423,961.00 John Petroff seconded the motion. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. 4) OTHER BUSINESS A) Pre -Bid & Bid Opening for Bid Packages #52-#66 (Info.) B) Security for Lansing Center - after hours The Board discussed the Committee's recommendation for an increase in after hours security at the construction site, due to the fire started a few weeks ago which destroyed a few new exterior doors. Ken Lawless has been checking on the costs for hiring additional security and presented the Board with the following cost quotations: TSC Security - $ 8.00/hr Annand Security - $ 7.95/hr After discussion about the approximate hours of security coverage necessary and knowing that TSC currently performs security at the Lansing Center, the following motion was made: Motion - Kathryn Haar motioned the Board to approve hiring TSC Security for after hours security at the Lansing Center. An amendment to the motion was made that coordination of security hours necessary be determined by Clark Construction in coordination with the Lansing Center administrations security. YEAS: Belen; Haar; Porter; Petroff; Mills Motion carried. C) Construction to be complete on the 2nd floor meeting rooms, east of the main rotunda by mid-January, 1994. Construction is anticipated to be completed on the 2nd floor meeting rooms, west of the main rotunda by the end of March, 1994. No motions made. D) Builder's Risk Insurance policy - discussion should take place with Bob Reid regarding turning over the 1st floor meeting rooms and 2nd floor meeting rooms east of the rotunda in January, 1994 to the current Lansing Center administration. The builder's risk policy should be modified to indicate such. No motions made. 5) PUBLIC COMMENTS None. 6) ADJOURNMENT Chairman Belen declared the meeting Minutes by P. Cook adjourned at 12:55 p.m. Emerson B. Ohl, TIFA