HomeMy WebLinkAboutBuilding Board of Appeals 2015 Minutes "`S ��: DEPARTMENT OF PLANNING AND
NEIGHBORHOOD DEVELOPMENT
316 N. Capitol Avenue, Suites C-1 • Lansing MI 48933-1238
(517)483-4355•FAX: (517)377-0169
BUILDING SAFETY OFFICE
Virg Bernero, Mayor
OFFICIAL PROCEEDINGS OF THE CITY OF LANSING
BUILDING BOARD OF APPEALS
Held at 316 N. Capitol Ave. at 2:00 pm
December 8, 2015
The December 8, 2015 meeting of the City of Lansing Building Board of Appeals was called to order at
2:15 PM. by Chairman Don Heck. The following members were in attendance:
Don Heck, Chairman
James Drake, Vice Chairman
Barry Wood
Tom Knoy
Members Absent: Chad Powers
Staff Present: Marshaun Blake, Fire Marshal =
Jon Snyder, Plan Review Analyst/Secretary `a
Chad Wakley, Building Inspector
Petitioners Present: Ken Jones, Studio Intrigue
Public Present: None
Chairman Don Heck asked for the approval of the November 10, 2015 meeting minutes. Barry Wood
made a motion to approve the minutes. Motion seconded by Tom Knoy. Motion carried unanimously.
Old Business: None
New Business:
Case No.: Address: Petitioner:
BBA-005-2015 1218 Turner Street Ken Jones
(These minutes of the Building Board of Appeals are not intended to be a transcript.)
Chairman Don Heck (HECK) gives an introduction of the appeal stating the petitioner was not yet present
and that Ken Jones (JONES) is asking for relief from section 1208.2 Michigan Building Code 2012 ceiling
heights.
Chad Wakley (WAKLEY) states that he was at the location for inspection and found a food prep area
being built without a building permit. He submits a site plan of the area showing ceiling height
measurements as low as 6 feet 5 inches.
Marshaun Blake (BLAKE) states that the biggest issue is that no permits were pulled and the plan review
process was skipped for this specific area of concern.
HECK calls for a pause in the meeting to try to contact the petitioner to see if he will be attending the
meeting.
HECK calls the meeting to order now that JONES is present.
JONES gives a brief introduction of the food prep area stating that putting in another door giving two
means of egress and installing smoke detection would make the area safer.
HECK states that different ceiling heights were given and all of them were below the required 7 feet.
BLAKE states the reason for plan review is to prevent situations like this. Also regarding the ceiling
heights he brings up that fire fighters have a wide variety of heights and there are important reasons for
having a minimum ceiling height in the Code.
Discussion ensues regarding the building being over 100 years old, the basement being used for storage
and the fire rating of the basement ceiling.
James Drake asks if it would make sense to table this issue to give JONES time to review options and to
submit plans to bring to code.
Jon Snyder asks if the food prep area is currently being used.
WAKLEY states that he told them they cannot occupy the area but is not sure it is not being used.
HECK asks JONES if he would want a definitive answer from the Board or to table the matter to have
more time.
JONES answers he would prefer to have more time.
Tom Knoy (KNOY) makes a motion to table the meeting.
Motion supported by Barry Wood (WOOD).
Motion carried unanimously.
It is agreed that JONES can submit construction documents 5 business days before the meeting for plan
review.
Other Business: None
Public Comment: None
James Drake makes a motion to adjourn.
KNOY and WOOD support.
Motion carried unanimously.
Respectfully submitted,
Jon Snyder, Secretary Draft date: 12/23/2015
Approved date: 1/12/16
cc: Mayor's Office Board Secretary
City Clerk's Office Building Safety Office Staff Representatives
Appeal folders Appeal applicants
Public file-original
S 1�G Department of Planning and
Neighborhood Development
316 N.Capitol Ave.,Suite C-1—Lansing,Ml 48933-1238—(517)483-4355—Fax(517)377-0169
Robert Johnson,Director
!c H t www.cityonansinami.coni
Virg Bernero,Mayor Building Safety Office
July 23, 2015
To: City Clerk's Office
City Council Off-ice
City Hall Personnel
Mayor's Office
From: James Bennett
RE:
BUILDING BOARD OF APPEALS
MEETING CANCELLATION NOTICE
The regularly scheduled Building Board of Appeals Meeting for August 11, 2015, has been
cancelled.
The next regularly scheduled meeting will be September 8, 2015, at 2:00 pm in the Building
Safety Office located at 316 N. Capitol Avenue, Suite C-1, Lansing, MI.
Cc: Board Members (4)
Building Safety Lobby
Board Secretary
Appeal folders
Applicants
Public file - Original
y� S I NG Department of Planning and
ment�
Neighborhood Development
p
316 N.Capitol Ave.,Suite C-1—Lansing,MI 48933-1238—(517)483-4355—Fax(517)377-0169
Robert Johnson,Director
I C H I www.cityoflansin-mi.com
Virg Bernero,Mayor Building Safety Office
May 27, 2015
r~m �
To: City Clerk's Office
City Council Office
City Hall Personnel C C7
Mayor's Office co
From: James Bennett 1--
o
RE:
BUILDING BOARD OF APPEALS
MEETING CANCELLATION NOTICE
The regularly scheduled Building Board of Appeals Meeting for June 9, 2015, has been
cancelled.
The next regularly scheduled meeting will be July 14, 2015, at 2:00 pm in the Conference Room
at 316 N. Capitol Avenue, Suite C-3, Lansing, MI.
Cc: Board Members (4)
Building Safety Lobby
Board Secretary
Appeal folders
Applicants
Public file - Original
0� LA DEPARTMENT OF PLANNING AND
NEIGHBORHOOD DEVELOPMENT
316 N.Capitol Avenue,Suites C-1 • Lansing MI 48933-1238
(517)483-4355• FAX: (517)377-0169
�fy. 1-1IGI`� BUILDING SAFETY OFFICE
Virg Bernero, Mayor
OFFICIAL PROCEEDINGS OF THE CITY OF LANSING
BUILDING BOARD OF APPEALS
Held at 316 N. Capitol Ave. at 2:00 pm
November 10, 2015
The November 10, 2015 meeting of the City of Lansing Building Board of Appeals was called to order at
2:10 PM. by Chairman Don Heck. The following members were in attendance:
Don Heck, Chairman
James Drake, Vice Chairman
Barry Wood
Tom Knoy
Members Absent: Chad Powers
Staff Present: James Bennett, Building Official
Jon Snyder, Plan Review Analyst/Secretary
Tony Phillips, Fire Inspector
Petitioners Present: Lingg Brewer -
Rick McKinstry c ) '
Kevin McIntyre
tv n
Public Present: None - e
r
Old Business: None
New Business:
Case No.: Address: Petitioner:
BBA-003-2015 308 E. Grand River Ave. Lingg Brewer
(These minutes of the Building Board of Appeals are not intended to be a transcript.)
Chairman Don Heck (HECK) asked everyone to introduce themselves. Introductions were made.
HECK asked for the approval of the September 8, 2015 meeting minutes. James Drake made a motion
to approve the minutes. Motion seconded by Barry Wood. Motion carried unanimously.
Rick McKinstry (MCKINSTRY) gives brief history of the building and has plans to renovate ten
apartments and one retail space. MCKINSTRY states that there are windows on the east side of the
property that are within five feet of the property line. He states the Building Code does not allow
windows in a building within zero to five feet of the property line. MCKINSTRY states that the building will
be fully sprinklered and they would provide a fully sprinklered window curtain at the openings, similar to
what they did on the old Rycus Floor building.
Tom Knoy asks about the precedence set at the Rycus building.
MCKINSTRY states the situation is very similar in relation to the windows on the second floor
overlooking a parking lot.
It was discussed that the Rycus building was different in that the windows were fire rated.
Jim Bennett (BENNETT) states that the Rycus building did not have smoke detection like 308 E. Grand
River will have as a trade off.
BENNETT talks about the benefit of getting a permanent easement from the owner of the parking lot so
no one could build next to the building.
Kevin McIntyre states they are currently in negotiations with the owner to these regards.
HECK states the issue is the windows on the property line, and the solution is to sprinkle the windows.
HECK asks Tony Phillips if he had any issues and he answered as long as the windows are sprinklered
then he has no issues.
Tom Knoy makes a motion to approve the request.
Motion supported by Barry Wood.
Motion carried unanimously.
Other Business: None
Public Comment: None
Respectful ub fitted,
C�
in Snyder, Secret ry Draft date: 11/23/2015
Approved date: 12/08/15
cc: Mayor's Office Board Secretary
City Clerk's Office Building Safety Office Staff Representatives
Appeal folders Appeal applicants
Public file-original
��� LA�'sl-�� DEPART MENT OF PLANNING AND
NEIGHBORHOOD DEVELOPMENT
:R
` 316 N. Capitol Avenue,Suites C-1 • Lansing MI 48933-1238
(517)483-4355• FAX: (517)377-0169
4.� -1..f1G
BUILDING SAFETY OFFICE
Virg Bernero, Mayor
OFFICIAL PROCEEDINGS OF THE CITY OF LANSING
BUILDING BOARD OF APPEALS
Held at 316 N. Capitol Ave. at 2:00 pm
September 8, 2015
The September 8, 2015 meeting of the City of Lansing Building Board of Appeals was called to order at
2:00 PM. by Chairman Don Heck. The following members were in attendance:
Don Heck, Chairman
James Drake, Vice Chairman
Barry Wood
Chad Powers
Tom Knoy
Members Absent: None r'
Staff Present: James Bennett, Building Official �` _w MI
Jon Snyder, Plan Review Analyst/Secretary r CD
Petitioners Present: Marry Swanson
Douglas Cook
Public Present: None
Chairman Don Heck asked for the approval of the March 31, 2015 special meeting minutes. Barry Wood
made a motion to approve the minutes. Motion seconded by James Drake. Motion carried unanimously.
Old Business: None
New Business:
Case No.: Address: Petitioner:
BBA-002-2015 1925 Turner Street Douglas Cook
(These minutes of the Building Board of Appeals are not intended to be a transcript.)
Chairman Don Heck (HECK) asked everyone to introduce themselves. Introductions were made.
Mary Swanson (SWANSON) gives brief history of when Mr. Cook purchased the property and that the
offices were existing and a mezzanine was then constructed by him. She states Mr. Cook started the
work without any permits. She states that only the back half of the mezzanine meets ceiling height
requirements.
Douglas Cook (COOK) states he knows he was wrong to begin work without permits and that he really
did not know proper procedure, but is asking for variance.
HECK asks COOK the heights of the mezzanine.
SWANSON answers 8 feet to 6 foot 3 inches.
HECK asks Jon Snyder (SNYDER) is there any additional information missing.
SNYDER answers that the existing offices were not built when the original building was built. There were
no other permits pulled to construct these offices until this year, therefore the offices were built illegally.
SNYDER brings out copies of the original construction documents showing no offices or furnace room-,
and the proposed drawings from Mary Swanson showing the mezzanine on top of these spaces.
The members and petitioners review the construction documents.
HECK confirms from SWANSON that the actual ceiling heights in the mezzanine range from 7 feet 7 112
inches to 6 feet 6 inches. This gives approximately 50% of the mezzanine area as being non-compliant.
Members and Petitioners discuss many options that were explored.
Barry Wood (WOOD) states that from an historical perspective he has issues with this. He has seen a
lot of developers that make changes and then ask for forgiveness. He states he has a fundamental
problem with that.
WOOD makes a motion to deny the request due to the fact that there exist other options for meeting the
code. This does not meet a request for hardship.
Motion seconded by Chad Powers.
Motion carried unanimously.
Other Business: None
Public Comment: None
James Drake moved to adjourn. Motion seconded by Chad Powers. Motion passed unanimously.
Respectfully'sub ted
n Snyder, Secretary Draft date: 9/08/2015
Approved date: 11/10/2015
cc: Mayor's Office Board Secretary
City Clerk's Office Building Safety Office Staff Representatives
Appeal folders Appeal applicants
Public file-original
Sr Department of Planning and
j Neighborhood Development
316N.Capitol Ave_.Suite C-I -Lansing.M118933-1238 -(i17)-IS3-13ii Paz(�17)377-0164
?j ?/ Robert Johnson. I)ircctor
\ �] G \\\ttt.Cit ullansim mi.com
Virg Bernero,Mayor Building Safety Office
November 23, 2015
The next regular meeting of the BUILDING BOARD OF APPEALS will be rescheduled
and held on, December 8, 2015 at 2.00 p.m. in the conference room located in the
Building Safety Office at 316 N. Capitol Avenue, Suite C-1, Lansing, Michigan 48933.
MEETING AGENDA
Roll Call
Excused Absences
Approval of Minutes: Approval of November 10, 2015 Meeting.
cTs .b: ~rl
Old Business:
None
New Business:
Case No: Address: Petitioner:
BBA-005-2015 1218 Turner Street Kenneth Jones
Other Business
Public Comment
Adjournment
IT IS ANTICIPATED THAT EACH CASE WILL TAKE APPROXIMATELY 15-20
MINUTES. THEREFORE, THOSE INTERESTED IN THE APPEALS SHOULD
ADJUST THEIR TIME ACCORDINGLY.